Rain for Rent Home Agriculture Products Irrigation Rienke Pivots Wheel Moves Wheelmove Specs All Ag Lines... Bins and Containers 25 yard Vacumn Box Crown Rolling Lid OR2 Intermodal Tube Settler All Containers... Filtration Systems Particulate (PF) Filters Bag (BF) Filters Sand Media Filters Portable Filters All Filtration... Freeze Sentry Instrumentation Oil Water Separators Pipe - HDPE/Aluminum HDPE Pipeline Aluminum Pipeline Fittings Fusion Machines Road Crossings All Pipeline... Pumps Centrifugal Pumps High Head Centrifugal Pumps Submersible Pumps Sound Containment Pump Testing Pump Training All Pumps... Spill Containment Tanks, Steel & Poly Polyethelene Tanks Steel Tanks (FRAC) All Tanks... Find Solutions Agriculture Bypass Pumping Construction Dewatering Mining Oil and Gas Industry Oil Water Separation Environmental Solutions Refinery Solutions Solutions for Pumps Solutions for Tanks Spill Containment Filtration Systems Solutions by Type About Us Office Locations Careers with us Customer Service Contact Us Arrange for a Demo Provide Feedback Find a Solution Expert Quality and Safety Search our Site Customer Login
|
Trash Pumps using Spill Prevention Control and HDPE Pipe Bypass Fragile 173 Year Old Dam
In mid October, 2005, the rising water level upstream put excessive pressure on the wooden structure. Downstream from the dam, the channel of the Mill River gets quite narrow. If the dam failed, the city leaders feared that it could unleash a 6 foot high wall of water. As a precautionary measure, 1,800 local residents and businesses were evacuated due to the threat of failure. A majority of dams in Massachusetts are still privately owned and maintained by landowners. It is the responsibility of the owners to regularly maintain and schedule inspections on all reservoirs. Despite regular inspections, numerous dams are quite antiquated and in need of major repairs or replacement.
Dick Pilotte, Branch Manager, and Matt DelMonte, Sales Representative, assessed the situation and suggested a pumping system that consisted of three, DV-300i Sound Attenuated (SA) and two, DV-200c Power PrimeTM pumps that moved 30,000 GPM from the upstream portion of the dam and reduced the hydraulic pressure on the structure. To maximize the flow and keep pipeline velocities at a safe level, Rain for Rent Engineers designed the system using fusable HDPE piping for all suction and discharge assemblies. This allowed access to the mechanical portion of the dam, so the floodgates could be raised and the dam slowly disassembled. Within an hour of notification to proceed, Rain for Rent assembled an emergency response team and worked overnight to install the system that pumped the 30,000 GPM of water around the dam. The U.S Army and Reserves provided additional help with hoses and fittings on site. If heavy equipment was preoccupied, the Army and Reserves helped to manually move large hoses to hasten assembly time. Overnight the two DV-200c and three DV-300i SA pumps efficiently moved the water around the dam, alleviating 10% of the water flow, which allowed access to the floodgates for careful removal of the old dam. As a safety precaution a secondary dam, constructed of large boulders, rip-rap and 48 inch concrete conduit was installed to reduce the risk of failure as the old dam was removed. Rain for Rent provided on site pump operators and mechanics for the duration of the project to ensure the system ran smoothly. In the aftermath of the fall rainy season encountered in New England, Rain for Rent helped design and install bypass sewer systems, pumped basements, and assisted with infrastructure repairs for local contractors and municipalities with their extensive fleet of self-priming pumps, knowledgeable staff, and 24-hour emergency service.
|
||||
|
|||||